Mingde homepage| Integrated Service Portal| Library| Principal and secretary mailbox| m88 online sports betting m88 live casino and sports betting
m88 best betting website
Management Measures for Completion Acceptance and Warranty Work of Infrastructure Projects of Xi'an Mingde Institute of Technology
2020-12-17 Ma Xiaojing 点击:[]

Chapter 1 m88 best betting websiteGeneral Provisions

Article 1 To standardize the completion acceptance and handover of the college’s infrastructure project、Warranty work,Improving relevant supervision mechanisms,Ensuring the quality of infrastructure project acceptance、Delivery time limit,In accordance with the laws and regulations of the country and governments at all levels and the relevant regulations of this hospital,Develop these measures。

Article 2 This method applies to the infrastructure projects referred to in the college's "Infrastructure Project Management Measures"。

Article 3 Referred to as completion acceptance in these regulations,refers to the coordination by the Infrastructure Operation Section of the Logistics and Security Department of the college on behalf of the college、Organization、Participate in the acceptance of individual projects and the completion of all projects;The so-called handover refers to the project that has been completed and accepted byInfrastructure Operation Science and Engineering DepartmentTransfer of (unit);The so-called warranty refers to the supervision of the Infrastructure Operation Department、Coordinate the work of infrastructure m88 online bettingproject m88 slot machine casinowarranty units in fulfilling warranty responsibilities。

Article 4 Infrastructure Operation Section is organizing the completion acceptance and handover of infrastructure projects、Strict standards must be maintained in warranty work,Standardized Procedure,Complete file,Accept supervision。

 

Chapter 2 Complete acceptance of engineering projects

Article 5 After the construction unit completes all the project contents in the construction contract,Submit project completion report to the supervision unit,The supervision unit shall report to the Infrastructure Operation Department of the college to prepare for the completion acceptance of the project。

Article 6 Infrastructure Operation Section organizes project completion acceptance。Infrastructure Operation Section Organization Project Utilization Department、Infrastructure Office、Finance Department、Archives Room、Design、Survey、Supervision and engineering construction units conduct physical inspections and internal inspections of project materials,Conduct preliminary acceptance,Enable the project to meet the conditions for completion acceptance。

Article 7 The completion acceptance of the project should meet the following conditions

(1) Complete the design of the infrastructure project and all aspects agreed in the contract;

(2) Have complete technical files and construction management information;

(3) Main building materials used in projects、Building components、Equipment quality inspection certificate and site test report;

(4) Inspection available、Design、Quality qualification documents signed by construction and engineering supervision units respectively;

(5) There is a project warranty signed by the construction unit.

Article 8 Special acceptance of engineering projects including acceptance of project completion files、Project fire acceptance、Project civil air defense acceptance、Project completion acceptance、Project completion acceptance。

Article 9  The project completion file formed by the construction unit compiling the completion data,Should be in accordance with the relevant provisions of the college's "Infrastructure Project Archives Management Measures",Two sets of copies submitted to the Infrastructure Operations Section,The Infrastructure Operations Department and the College Archives Office will conduct the acceptance of project files、Archived。
Article 10  Under construction,Infrastructure Operation Section should be based on the province、Municipal regulations on fire protection,Coordinate with the supervision unit in a timely manner、The construction unit conducts a comprehensive self-inspection of individual fire protection projects。After completion,Should promptly entrust a fire protection testing agency to conduct testing。After passing the test,Report to the government fire management department for acceptance。After passing the acceptance,All information should be filed and archived。
Article 11 The acceptance m88 best betting websitem88 online bettingof civil air defense projects is organized by the Infrastructure Operation Department,Supervision unit、Construction units jointly participate。Civil air defense project acceptance,Requires civil air defense acceptance of construction projects with civil air defense facilities and timely filing of acceptance results and related information。
Article 12  After completion of the project,The Infrastructure Operation Department should submit an application for project quality inspection to the Municipal Construction Engineering Quality Inspection Center in a timely manner and sign relevant agreements,Testing the indoor environment of the project according to the agreement。The test results will be used as the basis for indoor environmental testing and acceptance of the project。
Article 13 After preliminary acceptance of qualified parts of the project,The Infrastructure Operation Section shall apply to the government engineering quality supervision and inspection management department and agree on a time for the formal completion acceptance of the project。
Article 14 The completion acceptance of the project is under the supervision of the government’s quality supervision, inspection and management,Organized by Infrastructure Operations Section,Supervision unit、Construction unit、Surveying unit、Design units and related units jointly participate。The acceptance results and related information will be used as the basis for the completion acceptance of the project。


Chapter 3  Transfer of project

Article 15  After the project is completed and accepted,The project can be handed over。
Article 16  The transfer of engineering projects refers to the infrastructure operations department handing over the infrastructure projects that have passed the acceptance inspection to the asset management department,Includes total asset transfer(Including fire protection system、Civil air defense projects and large equipment, etc.)、Transfer of project completion status、House key handover、Transfer of project completion drawings, etc.。
Article 17 Relocation of engineering projectsLeave it to the Logistics and Security DepartmentHost,Infrastructure Operation Section、Finance Department asset managers jointly participate,And conducted under the supervision of the disciplinary inspection and supervision department。
   Article 18  Project handover record sheet via Infrastructure Operations Section、After the signature and seal of the asset management department,As the basis for project handover。


Chapter 4  Project warranty

Article 19  According to the "Construction Project Quality Management Regulations" of the State Council,Our hospital’s infrastructure projects all implement a quality warranty system。When the construction unit submits the project completion acceptance report to the Infrastructure Operations Department,A quality warranty certificate m88 online sports bettingm88 best betting websiteshould be issued、Instruction manual。The quality warranty letter should specify the warranty scope of the infrastructure project、Warranty period and warranty liability, etc.。
   Article 20 The warranty period of the project shall be in accordance with the warranty period stipulated by the state。Specifically:

(1) Infrastructure Engineering、The foundation engineering and main structure engineering of a house building are the reasonable service life of the project specified in the design document。

(2) Roof waterproofing project、Bathroom with waterproof requirements、The anti-leakage warranty period of the room and exterior walls is5 years.

(3) Heating、Cooling system,The warranty period is two heating periods、Cooling period

(4) Electrical pipelines、Water supply and drainage pipes、The warranty period for equipment installation and decoration projects is2 years.

(5) The warranty period of other projects shall be agreed between the infrastructure operation department of the college and the construction unit。

Warranty period of infrastructure projects,Calculated from the date of completion acceptance。

Article 21 Problems that occurred during the project warranty period,It is a construction quality problem,The Infrastructure Operation Section supervises the maintenance of construction units。Man-made damage、The user is responsible for repairing obstacles caused by improper use and low-value consumables。Normal maintenance during the warranty period and normal repair after the expiration of the warranty periodResponsible for the Infrastructure Operation DepartmentResponsibility。Problems that occurred after the project warranty expired,Infrastructure Operation Department should assist the user unit to handle it properly,However, the construction unit does not bear warranty and financial responsibility。

Article 22 Under warranty,On-site representatives of the Infrastructure Operations Department should proactively conduct return visits and inspections on the projects they are responsible for,Supervision and supervision unit、The construction unit conscientiously implements the warranty terms stipulated in the project contract,And in accordance with the warranty period and content stipulated in the "Construction Project Quality Management Regulations" of the State Council,Do a good job in warranty work。

Article 23 When quality problems occur in the project within the warranty scope and warranty period,The Infrastructure Operation Department will instruct the construction unit to perform warranty obligations。If the construction unit fails to fulfill its warranty obligations,The Infrastructure Operation Department can arrange for other qualified construction units to take over the maintenance,And deduct the original construction unit’s warranty payment in accordance with the contract。

Article 24 After the project warranty expires,Project warranty expiration application report form m88 slot machine casinom88 online sports bettingsubmitted by the construction unit,Used unit、After signing and agreeing with the Infrastructure Operations Department,As the basis for final payment of the project and the end of the project warranty period。

 

Chapter 5 Supplementary Provisions

Article 25 The completion acceptance of sporadic maintenance projects within the college can be implemented with reference to these measures。

 

Previous article:Xi'an Mingde Institute of Technology Mingde College Infrastructure Project Budget and Final Account Management Measures

Next item:Measures for the Management of Infrastructure Project Files of Xi'an Mingde Institute of Technology

Teaching Team
Admissions and Employment
Talent Recruitment